Resolution 2248
RESOLUTION NO. 22490
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE
SOUTH TAHOE PUBLIC UTILITY DISTRICT ACCEPTING
AND FILING A NOTICE OF SUBSTANTIAL COMPLETION
FOR THE WASTEWATER RECLAMATION PLANT, HEADSTART
IMPROVEMENTS, PHASE I, TENTATIVE CERTIFICATE FOR
CLOSED VEHICLE STORAGE, LARGE OPEN VEHICLE,
STORAGE A14D EXISTING MAINTENANCE BUILDINGS.....
W. R. THOMASON, INC.
P.O. BOX 2249
MARTINEZ, CALIFORNIA 94553
RESOLVED by the BOARD OF DIRECTORS, SOUTH TAHOE PUBLIC UTILITY
DISTRICT, El Dorado County, California, that:
WHEREAS, the District Consulting Engineer, William F.
Ettlich, Culp/lVesner/Gulp, has filed with the Clerk of said
District, his TENTATIVE CERTIFICATE OF SUBSTANTIAL COP?PLFTION
for the:
Closed Vehicle Storage,
Large Open Vehicle Storage,
' and Existing Maintenance Buildings
contractor: W. R. Thomas. Inc.
P.O. Box 2249
Martinez, California 94553, and
WHEREAS, it appears to the satisfaction of the Board of
Directors that said work under said contract has been substantially
completed as of MARCH 18, 1982, (copy of Tentative Certificate of
Substantial Completion attached.)
NOW, THEREFORE, IT IS ORDERED:
(1) That acceptance of substantial completion
of said work be, and it is hereby made and
ordered, above mentioned contract, is
substantially completed.
(2) That the Clerk of Board of said District
is directed to execute and file with the
County of El Dorado, T.,Totice of Substantial
Completion, as reguie~ y law.
J R. Tones, Pr dent
/ th Tahoe Publ!J tility District
ATE S,
ja D. rse, Cerk of Boar
uth. Ta e Public Utility District
BOOK 2073 m685
I hereby certify that the foregoing is a full, true
and correct copy of RESOLUTION NO. 2248, duly and regularly
adopted by the Board of Directors of the SOUTH TAHOE PUBLIC
UTILITY DISTRICT, E1 Dorado County, California, at a meeting
thereof_ duly held on the ^6tth~ day of '!AY 1982, by the follow-
ing vote:
AYES: Directors ?ones, Madden and Wynn
NOES: None
ABSENT: Directors Kashuba and Olson
Clerk of/ oard and Ex-Officio Secretary
SOUTH T.. OE PUBLIC UTILITY DIS'T'RICT
C1F~~t;lh r ~Cu
SOtl1'N TWP BI Lit:
MAY 8 36 AM 1982
COUNTY R c :+JRBER
. cJ
V
jo
Bn2073 PAGE686
ENS W cocuAAuNT,
CERTIFICATE PROJECT C-06-1414-210-02
SUBSTANTIAL COMPLETION
. OW DATE April 2, 1982
Owner South Tahoe Public Utility District
Contractor W. R. Thomason, Inc. P.O. Box 2249, Martinez, CA 94553
Contract Headstart Program Improvements - Phase I
The work performed under this contract has been reviewed and found to be sub-
stantially complete. The date of substantial completion is designated as
March 18, 1982 The designated area or scope of
work is Closed Vehicle Storage, Large Dan V 'hi ri t, st-orageRuilrli ng and
existing Maintenance Building.
This date represents the commencement of any warranties or guarantees
under the conditions of the contract that are connected with the above
portion.of the project only.
The Date of Substantial Completion of the work is the date certified by the
Engineer and approved by the Resident Engineer when construction is sufficiently
complete in accordance with the contract documents to allow for the uninter-
rupted start and completion of subsequent subsystems in accordance with the
Construction Schedule.
A list of items to be completed or corrected, prepared by the Resident
Engineer and verified and amended by the Engineer, is attached. The failure
to include any items on such list does not alter the responsibility of the
Contractor to complete all work in accordance with the Contract Documents.
REMARKS
REFERENCE DOCUMENTS
List of items to be completed or corrected, compiled on March 18, 1982.
U1
LA
Attachments
.Signature Signature Si atur
r
Resident Engineer gineer ner
Culp/Wesner/Culp Culp/Wesner/Culp South Tahoe Public Utility
Date Date Date District
4- 2- $2 30 ' 8Z_
BmK PwA 75
HEADSTART IMPRO%TEI. ENTS - PHASE I
LIST Or ITEMS TO BE COMPLETED OR CORRECTED
COMPILED: MARCH 18, 1982
CLOSED VEHICLE STORAGE BUILDING
1. Remove snap tie plastic cone from inside face of north end of
colored concrete lintel over roller doors and fill the hole
with colored mortar.
2. Chip concrete floor level around conduits under power panel.
3. Remove nails and mortar up holes in inside face of concrete
block near 2nd and 3rd rear windows from north end.
4. Sandblast concrete masonry units at north end of colored
lintel over roller doors.
5. Remove concrete runs from outside face of concrete masonry
units below lst and 4th window from north end.
6. Patch and smooth down concrete overpour over concrete blocks
at south end of colored roller door lintel.
7. Plug temporary electric light cable hole to contractor's trailer
in north wall concrete masonry units.
8. Sandblast and clean off concrete runs on outside concrete
block faces around all rear windows. .
9. Remove temporary plywood partition between south bay and
all three other bays.
10. Top up caulk in both floor contraction joints, especially
the one under the temporary plywood partition.
11. Install drip cap and head and jamb weather stripping at
small north door.
12. Install weather stripping on roller door frame.
13. Cut off excess length of roller door frame holddown bolt on
LHS of second door from the north end of the building.
14. Check and reset upper limit switch on second roller door from
the north and lower limit switch on third roller door from
the north end of the building.
15. Install rubber weather seal flap inside roller door housing
on third roller door from north end of building.
16. Supply 2 keys for small north door.
17. Clean glass in small north door after it has been painted.
18. Clean green numbering off of outside face of second window
frame from north end of building.
w2073 PAGE076
2-
CLOSED VEHICLE STORAGE BUILDING (CONTINUED)
19. Paint inside of all roller doors and housing with minimum of
two coats.
20. Paint door and frame of small north door.
21. Paint vent fan housing and louver frame.
22. Paint all electrical panels, conduits and brackets.
23. Paint inside of roller door guide and threshold angle.
24. Paint inside of oil interception tank two coats of medium
consistency coal tar.
25. Paint ceiling.
26. Apply liquid waterproofing to inside walls.
27. Clean green paint off of blockwork around roller door opening.'
28. Clean overspray off light panel L--4 label.
29. Spray hardener on floor of fourth bay from north end of
building.
30. Install sink drain and water pipe with isolating stops at
north wall and check to see if floor drains are unplugged.
31. Install valve box in outside concrete pavement over main
outside building isolating valve.
32. Bracket both freezeproof hydrants to block wall behind them.
33. Remove tape from valve box cover.
34. Vent thermostat is missing and exhaust and inlet louver motor
are not interconnected to it.
35. Wire up safety stop on bottom of roller door and check and
tighten up all gear cog key setscrews.
36. Conduit wall clamp on north wall is not in proper position
and another conduit clamp is required higher up same wall.
37. Two outside low pressure sodium lights do not work.
38. Remove cable reels and unused electrical panels from north
bay.
39. Supply 100% replacement light bulbs.
BON2073 =677
SMALL OPE'% VEHICLE STORAGE BUILDING
23. Supply six spare 16" wide low pressure sodium outside wall
lights equipped with photoelectric cells (which were
delivered to site but not mounted on 12" wide front columns)
into District storage (as per Change Order No. 13).
24. Supply 100% replacement light bulbs.
LARGE OPEN VEHICLE STORAGE BUILDING
1. Remove nail from base of northeast column on outside stem
wall, east side of north doorway and base of third column
from north side.
2. Sandblast lower inside face of north concrete block wall to
remove concrete splatter.
3. Remove efflorescence from inside face of west block wall and
top inside face of south block wall.
4. Paint mortar in lintel block joints over south doorway and
wire brush efflorescence in previous painting work done in
this vicinity.
5. Remove excess mortar at base of block wall at west side of
south doorway.
6. Finish off by plastering top of inside north and south block
walls, just under metal decking, to a smooth straight surface
cut flush at the top or cover top of wall with a painted
timber trim strip.
7. Replace missing sole plates under metal decking at the top of
the west wall.
8. Remove excess mortar on top of inside concrete stem wall
under fourth window from north end of the building.
9. Remove and repaint cracked mortar on inside wall face between
concrete masonry blocks under third and fourth windows from
north end of the building.
10. Plug holes in concrete block behind lighting panel on north
wall.
11. Blow off hydromulch blobs off of outside west wall.
12. Sandblast outside face of block wall around third and fourth
windows from north end of building to remove concrete splatter
from window eyebrow pour.
13. Top up caulk in floor contraction joints and remove surplus*
spill at east end of contraction joints.
14. Remove surplus caulk spill on outside concrete walkway joint
at southwest corner of building.
15. Clean outside window frames.
Boox2073 PAGE678
LARGE OB'E.. '.•_HICLE STO.'RACE BUILDING (CONTINUED)
16. Paint unpainted and too thinly painted column bumper and
threshold angle iron strips (coating thickness of painted
bumper guards is 2--3 mil. while 5 mil. minimum is required).
17. Paint all electrical panels, conduits and brackets.
18. Touch up stain in areas of eaves soffits which were stained
white by overspraying block moisture sealer.
19. Touch up thin stain spots along eaves soffits.
20. Apply liquid waterproofing to inside walls.
21. Eliminate bird baths from new A/C pavement between vehicle
storage buildings and maintenance buildings.
22. Outlet receptacle cover on inside west wall is missing.
23. Condulet cover in northeast part of ceiling is missing.
24. Panel locking key and cover plate bolt are missing from
light panel on north wall.
25. Two outside low pressure sodium lights do not work.
26. Remove electrical panels, emergency generator, automatic
transfer switch panel and pvc conduit stockpile from first
and second bays from north end of building.
27. Supply 100% replacement light bulbs.
EXISTING T~LAINTENANCE BUILDING MODIFICATIONS
1. Install insect screening around conduit entrance through eaves
soffit at southwest corner of building.
2. Remove temporary telephone wires from eaves and replace any
missing shingles in eaves.
3. Paint new conduit installed at southwest corner of building.
4. Touch up thin stain spots along eaves soffit.
5. Touch up thin trim stain spots along eaves and stain trim
in northeast corner with two coats of stain.
6. Paint new vent grill in eaves soffit on east side of building.
7. Obtain price for light sandblasting and painting (two coats)
both existing roller doors and both small doors and frames
on west side of building.
8. Remove debris from behind east side of building, including
former contractor's trailer pvc sewer connection pipe, etc.
9. Pump down and make good broken in new maintenance building
sewer interconnection at new sewer P•101.
m2o?3 FAA79
E`:ISTIN^ r AINT~.' n SCE BUILDING MODI PI CATI ONS (CONTINUED)
10. Remove existing incoming power and telephone conduits on
outside west wall and plug conduit at ground level and
where it penetrates the block wall.
11. Remove temporary power transformer in northwest corner
of north bay.
EE:evn
4--6-82
m2073 QaWO
CERTIFICATE PROJECT: C-06-1414-210-02
OF OCCUPANCY DATE : March 18, 1982
Owner: South Tahoe Public Utility District, South Lake Tahoe, CA
Contractor: W. R. Thomason, Inc., Martinez, CA
Contracti Headstart Program Improvements - Phase I
It is mutually agreed between the Owner and the Contractor to divide the
responsibilities for said partially utilized portion of the project in
the following manner, commencing on the date of occupancy or utilization,
which shall be taken as the date of definitive substantial completion.
The designated portion of the project utilized is the Closed Vehicle
Storage Building and the Large Open Vehicle Storage Building.
The Owner's responsibilities will be (a) to operate heating and ventil-
ating systems in above facility, (b) assume responsibility for power
requirements to above facility, (c) assume responsibility for property
insurance on occupied areas, (e) maintenance of the above facility in
regard to normal operations, (f) safety of District's personnel, and,
(g) shall allow Contractor reasonable access to the above facility to
complete or correct items on tentative correction list attached to
Substantial Completion Certificate.
The Contractor's responsibilities will be (a) allow access for owner's
personnel, (b) allow access for public, if applicable, (c) allow
operation of subservient heating, ventilating and electrical systems
even if outside occupied areas, (d) obtain the necessary endorsements
on their property insurance policy as set out in Paragraph 5.06 A of
the General Conditions, (e) safety of Contractor's personnel, and,
(f) warranties as outlined in the contract documents for the above
specific items to commence on the definitive substantial completion
date.
None of the above releases the Contractor of any of his obligations
to perform the work in accordance with the contract documents.
Unless otherwise agreed to in writing, and so inform the Engineer
prior to the issuing of the definitive Certificate of Substantial
Completion, the above division of responsibilities on the designated
partially utilized portions of the project will be binding on the
Owner and the Contractor until final payment.
Signature
Engin illiam F. Ettlich
Culp/Wesner/Gulp
DATE:-4 - 2 S 2
t
DATED: 4/30/82
STATE OF CALIFORNIA )
)ss
COUNTY OF EL DORADO )
On 4/30/82 before me, the
undersigned, a Notary Public in and for said State,
personally appeared WILLIAM F. ETTLICH
known to me to be the person(s) whose name(s) is
subscribed to the within instrument and acknowledged
that he executed the same.
WITNESS my hand and official seal.
M L/4 L i fir"
Notary/ Piiblic in and for the
State'of California, County of
El Dorado
My Commission Expires 11/19/82
AIMINL
#*ARY ORMA AM9
ROTA" KMC
U DOFADo CO. CAN/OMA
My Cortwhsto++ Expires Mm 19, 1"2
60DK2073 FAA82
DATED: 4/2/82
STATE OF CALIFORNIA )
)ss
COUNTY OF EL DORADO )
On 4/2/82 before me, the
s
undersigned, a Notary Public in and for said State,
personally appeared EDUARD EUYEN
known to me to be the person(s) whose name(s) is
subscribed to the within instrument and acknowledged
that he executed the same.
WITNESS my hand and official seal.
NotarryPublic in and for the
State of California, County of
E1 Dorado
My Comm'ssion Expires 11/19/82
AkMy D"" AM~p
NOTAW P1ALK
EL DORADO OO., CAIJ~OOE~
MY Can~sle:toos'xp~ras tdry.. 19, fi4g?
BOOK2073 PAGE683
DATED: 5/6/82
STATE OF CALIFORNIA )
) ss
COUNTY OF EL DORADO )
On 5/6/82 before me, the
undersigned, a Notary Public in and for said State,
personally appeared JAMES R. JONES
known to me to be the person(s) whose name(s) is
V"` subscribed to the within instrument and acknowledged
that he executed the same.
WITNESS my hand and official seal.
Notary Public in and for the
State of California, County of
El Dorado
Co . 5 11 Z1-9,14
2 .
NARY MWA AMOt'C M
y~ ~N~O/~T/I~t~~Yy~P W iK
U DORADO WY
~19, 1~
mrnm2073 ~ fi84
PRESIDENT
SOUTH TAHOE PUBLIC UTILITY DISTRICT JAMES R JONES
Sewer . 1950. Water A PUBLIC AGENCY DIRECTORS
P.O. Box AU South Lake Tahoe, California 95705 Phone (916) 544-6474 WALTER "NEAL" OLSON
LORRENEKASHUBA
1275 Meadow Crest Drive MICKEY MADDEN
JOHN WYNN
i
May 6, 1982
E1 Dorado County Recorders Office
330 Fairlane
Placerville, CA 95667
Gentlemen:
Attached please find the following documents with
attachments for recording, and please return to this office.
RESOLUTION NO. 2248
Certificate Substantial Completion
w/attachments
Certificate of Occupancy
Notary for all signatures
Thank you.
Very truly yours,
SOUTH TAHOE PUBLIC UTILITY DISTRICT
Mary I~. Ambrose
Clerk, of Board
mda
Attachments
W.R. Thomason, Inc
Box 2249
Martinez, CA 94553
(Closed Vehicle Storage, Large
Open Vehicle Storage and Existing
Maintenance Bldgs.)