Resolution No. 1819 WJML:RJH:np 6 -14 -73 8c
RESOLUTION NO. 1819
A RESOLUTION CALLING FOR SEALED PROPOSALS
AND FIXING LIQUIDATED DAMAGES FOR FAILURE
TO COMPLETE THE WORK WITHIN TIME SPECIFIED
ASSESSMENT DISTRICT 1971 -1
RESOLVED, by the' Board of Directors of the South Tahoe Public
Utility District, El Dorado County, California, that
WHEREAS, this Board did on the 6th day of April
1972, adopt its Resolution of Intention No. 1676 , as subsequently
amended, to order the construction of sanitary sewerage systems,
including trunk sewers, collection sewers, necessary pumping stations
and force mains, manholes, flushing devices, rodholes, wye branches
and all appurtenances; all as more particularly described and set
forth in said Resolution of Intention;
NOW, THEREFORE, the Clerk of said District is hereby directed to
publish once a week for two weeks in the Tahoe Daily Tribune, a news-
paper published and circulated in said District, a notice inviting
sealed proposals or bids for the construction of said improvements,
and referring to the plans and specifications on file in the office
of said Clerk, the first publication of which notice shall be at
leas't'fourteen days prior to the time fixed for opening bids.
All proposals or bids shall be accompanied by cash, a cashier's
or certified check payable to the order of the District amounting to
twenty percent (20%) of the bid, or by a bond in said amount and pay-
able to said District signed by the bidder and a corporate surety
or by the bidder and two sureties who shall justify before any officer
competent to administer an oath, in double said amount and over and
above all statutory exemptions. The amount so posted shall be for-
feited to said district in case the bidder depositing the same does
not, within fifteen days after written notice that the contract has
been awarded to him, enter into a contract with the District.
L
- .
It is hereby determined that in the event the contractor,. con-
4 - 110, tracting owners included, does not complete the work within the time
limit specified in the proposed contract or within such further time
as this Board shall have authorized, the contractor or contracting
owners, as the case may be, shall pay to the District liquidated
damages in the amount of One Hundred Thirty Dollars ($ 130.00
per day for each and every day's delay in finishing the work beyond
the completion date specified in said contract. Additional provisions
with regard to said time of completion and liquidated damages are set
forth in the specifications, which provisions are hereby referred to
and incorporated herein by reference.
Said sealed proposals or bids shall be delivered to the Clerk of
said District on or before 2 :00 o'clock P .m. on the 23rd day
of July , 1973, said time being not less than fourteen days
from the time of the first publication of said notice. Bids will be
publicly opened, examined and declared on said day and hour, and
referred to and considered by the Board at its meeting at 8:00
o'clock p.m. on July 23rd , 1973.
President
A TEST: South Tahoe Public Utility District
er and x o is o Secretary
* * * * *
I hereby certify that the foregoing is a full, true and correct
copy of Resolution No. 1Alq duly and regularly adopted by the
Board of Directors of the South Tahoe Public Utility District, El
Dorado County, California, at a meeting thereof duly held on the
21 day of Tune , 1973, by the following vote:
AYES, and in favor thereof, Directors: Wakeman
Fester
Hegarty
Ream
NOES, Directors: None
ABSENT, Directors: Kortes
Clerk and Ex officio Secretary
South Tahoe Public Utility District