Resolution 2620
~
~
~
RESOLUTION NO. 2620
2
3
4
A RESOLUTION OF THE BOARD OF DIRECTORS OF
SOUTH TAHOE PUBLIC UTILITY DISTRICT
CERTIFYING FINAL ENVIRONMENTAL IMPACT REPORT
AND APPROVING
SOUTH TAHOE PUBLIC UTILITY DISTRICT
A-LINE EXPORT PIPELINE RELOCATION PROJECT
5 BE IT RESOLVED, by the Board of Directors of the South
6 Tahoe Public Utility District, County of El Dorado, State of
7 California, as follows:
8 The Final Environmental Impact Report entitled
9 "STPUD A-Line Export Pipeline Relocation Project, Final
10 Environmental Impact Report, Environmental Impact Statement,
]] Environmental Assessment, SCH Number 94062040, June 30, 1995,
12 prepared by Harland Bartholomew & Associates, Inc." was presented
13 to the Board of Directors on June 22, 1995.
]4 Said Board of Directors does hereby approve and
15 certify the technical adequacy of the "STPUD A-Line Export
]6 Pipeline Relocation Project, Final Environmental Impact Report,
17 Environmental Impact Statement, Environmental Assessment, SCH
18 Number 94062040, June 30, 1995, prepared by Harland Bartholomew &
19 Associates, Inc.," South Tahoe Public Utility District
20 certifies that said Final Environmental Impact Report was prepared
2] and completed in compliance with the California Environmental
22 Quality Act and the State of California CEQA guidelines and local
23 guidelines adopted pursuant thereto.
24 The Board of Directors of South Tahoe Public Utility
25 District has reviewed and considered the information contained in
26 Final Environmental Impact Report entitled "STPUD A-Line Export
27 Pipeline Relocation Project, Final Environmental Impact Report,
28 Environmental Impact Statement, Environmental Assessment, SCH
Resolution No. 2620
Page 2
Number 94062040, June 30, 1995, prepared by Harland Bartholomew &
\.,. 2 Associates, Inc.," prior to taking any other action this date
3 relating to A-Line Export Pipeline Relocation.
4 The Board of Directors of the South Tahoe Public
5 utility District hereby requires that all measures developed to
6 mitigate significant impacts of the proposed action are contained
7 in Chapter 3 of this Final EIRjEIS/EA and are hereby incorporated
8 into the Preferred A-Line Pipeline Relocation Alternative, which
9 apply to the South Tahoe Public utility District are hereby
10 considered Conditions of Approval for this project.
11 NOW, THEREFORE, BE IT FURTHER RESOLVED, by the BOARD OF
12 DIRECTORS of the SOUTH TAHOE PUBLIC UTILITY DISTRICT that:
13 Said Board of Directors does hereby approve as the A-Line
14 Export Pipeline Relocation Project, the plan identified as
'" 15 Alternative 4 in "STPUD A-Line Export Pipeline Relocation Project,
16 Final Environmental Impact Report, Environmental Impact Statement,
\..
17 Environmental Assessment, SCH Number 940620'40, June 30, 1995,
18 prepared by Harland Bartholomew & Associates, Inc.," for South
19 Tahoe Public Utility District.
20 PASSED AND ADOPTED by the Board of Directors of South
2] Tahoe Public Utility District at a duly held regular meeting on the
22 6th day of July, 1995 by the following vote:
23
24
25
26
27
28
AYES: Strohm, Mason, Wallace, Jones, Mosbacher
NOES: None
ABSENT: None
~~ ~rf2~
DUANE WALLACE, PRESIDENT OF THE BOARD
SOUTH TAHOE PUBLIC UTILITY DISTRICT