Clement PTAS_preliminary relocation cost estimateFrom:Jennifer Lukins
To:Ivo Bergsohn; Sachi Itagaki; Robert Haen
Subject:Fwd: Clement
Date:Friday, August 23, 2019 3:49:49 PM
Hi Ivo and Sachi,
Please see the very rough estimate below to move the air stripper from Clement. Please keepin mind that these numbers are NOT prevailing wage, and are based on privately funded
project. I think you can safely estimate a additional 30% if it were a public project.
---------- Forwarded message ---------From: Robert Haen <rhaen@thomashaenco.com>
Date: Fri, Aug 23, 2019 at 3:42 PMSubject: Clement
To: Jennifer Lukins <jennifer@lukinswater.com>
Partial Demo and rebuild of clement tower- $50,000
Lift Out Tower, Transport and Set in Place $32,000Mechanical Work- $40,000
New Building for Tower at Lukins- $160,000Intertie New System to Existing Piping- $20,000
Electrical work- $12,000
--
Jennifer LukinsLukins Brothers Water Company, Inc.
(530) 541-2606
This email and any attachments hereto may contain confidential and/or privileged subject matter. If you have received this
communication in error, please delete it immediately.
This email message has been delivered safely and archived online by Mimecast.