05152017 OPS1
OPERATIONS COMMITTEE MEETING
Monday, May 15, 2017
2:30 p.m. Conference Room 1st Floor
Present: John Thiel, Shannon Cotulla, Richard Solbrig, Jim Jones, Heidi Baugh
Public: None
A meeting was held to discuss the following:
TOPICS DISCUSSION
1. PUBLIC COMMENTS None.
2. CONSTRUCTION PROJECTS
a) LPPS Power
and Controls
Thomas Haen Co)
Continuing work on electrical and controls component of this project.
If all goes according to plan the 60-day test will start on Friday.
Pump 3 is being rehabbed to the tune of approximately $92,000 worth of work. We
expect to receive it back by early July.
Financing period for this project ends by the end of August, so we need to have this
project completed by then for use of grant funds.
Still some demolition and site work left for Thomas Haen Company to complete.
Contractor is contending with high groundwater so he may need to hold off for a little bit.
We have been waiting to receive a schedule from the contractor for a timeline of this
final work.
b) DVR Irrigation/
C Hydro (
Thomas Haen Co)
Contractor (Thomas Haen Company) is building some of the intertie assembly for the
north intertie which is scheduled for the first week in June.
Most of the contractor’s crew was at the Tahoe Keys pump station helping with our
emergency the last few weeks.
June 5 is the week we have scheduled to do the shutdown for the north intertie work.
During this shutdown our crews will conduct some maintenance on the C-Line and LPPS
piping as well.
c) Primary
Clarifier
1/Aeration Basin 2
Rehab Project
The contractor, Farr Construction/RDC is on site and making good progress.
They have completed the sandblasting prep of Aeration Basin 2, and are starting the
coating process.
d) 2017 Water
Meters Installation
Project
Opened bids last Friday. We received only one bid. We were expecting two since we
had received two bid bonds. The bid we received is only 8% over the engineer’s
estimate and looks to be a fair bid.
We will bring our recommendation to the Board at the June 1st meeting. We plan to start
work in mid-June.
The State loan contract is actually with our attorneys! There is a new stipulation that
entails a 16% match. Lynn is investigating to see what we can use for match.
e) 2017 Hydrants
and Large Meters •
Opened bids Tuesday, May 9. We received two bids, with White Rock Construction
being low. They completed the previous hydrants project for us.
Staff will be recommending award to White Rock Construction even though the bid came
in quite a bit over our engineer’s estimate, largely due to the large meters component.
Staff will be doing some in-house value engineering in an effort to reduce the costs of
the meters portion of this project.
f) Ponderosa
Waterline •
We had 5 general contractors attend the Pre-Bid Meeting and four registered for the dbe
good faith effort process and are eligible to bid.
Bids will open May 23rd. Expected mobilization is July 10th.
2
3. PLANNING / DESIGN
a) Plant
Emergency
Generator (2018)
HDR
HDR is working on the 100% design.
We are pursuing private financing for this project due to the SRF delays and unknowns.
Paul Hughes estimates we should be able to secure this by the end of the year.
Lynn may approach FEMA and apply to have some of these costs covered through them
we had to use it so much during the storms). We could possibly receive $200,000-
400,000 toward this work.
Our schedule has us advertising for construction this fall.
We anticipate having this project in motion by early May 2018.
The new generator will be located in front of Operations in the reveg’ed, wooded area.
b) Keller-Heavenly
Zone Improve-
ments
Farr West)
Farr West is working on completion of the Technical Memorandum, after which they will
start on the detailed design utilizing El Dorado County Water Agency funds.
We will schedule a tour of these sites for next month’s Operations Committee meeting.
c) Groundwater
Management
Planning
South Y Remediation Alternatives – we received about $300,000 in Prop 1 Grant
funding for which the match has already been met by the District. RFP should go out in
the very near future.
Water Board has issued a Cleanup and Abatement Order to the responsible party, Lake
Tahoe Laundry Works.
d) Flagpole Tank
Rehabilitation
HDR
Rehab design is in progress.
We are still waiting on the Final Technical Memorandum from HDR. The rehab coating
system will be a mortar repair system with epoxy-based overcoat.
Farr Construction California, the contractor doing our PC1/AB2 Rehab project, will likely
do this work under a change order.
4. OTHER
a) Engineering
Staffing Update •
Limited Term Jr. Engineer has been hired to replace Brent. Our last intern, Tiffany Racz,
was hired for this position.
Our new intern will be starting at the end of the month. He is a local who just graduated
from UNR.
Tim Rieger has given his retirement notice and will be leaving in July. We are advertising
for his position.
Wanda Stanley has given her retirement notice and will be leaving in August.
Garth Butz will be helping with inspections work this summer.
b) Tahoe Keys
Emergency Sewer
Repair
District crews installed 18 pieces (80’) of 4.5’ long PVC pipe segments with glue-on
fittings.
Pipe installation started Wednesday (5/10) and was mostly by end or day Thursday.
Crews conducted backfill Friday. Paving, curb and gutter are left to be completed. We
are in contact with SNC to complete this work as they are now in town doing similar work
for the City.
c) Other: Big 5 Pump Stations: RFP for “Big 5 Pump Station Condition Assessment” project is on
the street as of today (5/15). This project was accelerated due to recent storm impacts.
Lakeside Park: They will be doing rehab work on their tank in next the few weeks. We
will open our intertie at Stateline and Cedar and provide all of their water during their
shutdown period. We expect to have it open for 4-6 weeks. They want to have their work
done by July 4th when they see peak demand. We are also working on a Mutual Aid
Agreement with them (similar to what we have with Tahoe Keys and Lukins Bros. Water
Company).
McDonald’s: – (at the Y) is tearing down their building at the Y and replacing with a
3
completely new structure. Working with them on new fire system and connection issues.
Whole Foods: the area between Ski Run and Herbert (where the Knight’s Inn and Mo’s
Place are currently). They will be demoing the existing buildings to build a Whole Foods
store with a few other standalone buildings. This will entail taking care of some of the
issues upstream of that area, which will include the trailer park where we had so much
trouble with I&I during the storms this winter. Also, District has a 1” dead-end service line
that we need to determine whether to abandon or incorporate into this project. John will
discuss this further with Julie. They are hoping to do the demo and install foundation this
season (pretty optimistic).
Gondola Vista: – is a project that entails developing 11 high-end duplexes (next to van
sickle park). District will need to drive through this development to access our Stateline
Tanks.
Lake Tahoe Wildlife Care: – Working with Jim Ferguson on connections to the water
and sewer system. They are installing a new manhole at their sewer connection at the
end of Matheson Drive. They will need some pumping on their end to get it there.
Fallen Leaf Lake: – The Tahoe Keys work has delayed our work at FLL. Now that the
Keys is getting buttoned up, we will turn our focus to FLL. We intend to go in from the
main station and install four 2” lines - two to VV4, and the other two will be for future
extension to VV3 which is located up by the Fire House. Crews are staging equip and
materials now. As soon as the weather breaks they will get started on it. Shannon
anticipates we will be receiving calls from “concerned citizens” because of the proximity
to the lake. Our main focus is Station 4 - which is right on the Lake - eliminating the
vacuum valve and getting that turned into an electrical station. We will get as much done
before Memorial Day as we can. Probably at least get the trench work completed.
5. ADJOURNMENT
Next Ops Mtg. Next Operations Committee meeting will be held on Monday, June 12, 2017.