PDI Access Agreement Information-KJ-020118South Y Feasibility
Pre-Design Investigation
Site Access Agreement Information
Liberty Utilities (APN 023-30-111; 933 Eloise Avenue)
The proposed work site for the test well drilling program would encompass an area of approximately
##,###5,500 sf (70’x 77’) on the Liberty property (APN 023-30-111); and ##,### 4,000 sf (57’x77’) on the
City of South Lake Tahoe (CSLT) property (APN 023-30-109) shown in red shading above. The drilling and
testing equipment, support vehicles, materials and supplies would be set-up on the paved are of the
Liberty property. The Test Well will be located on the CSLT property. Storage tanks for the temporary
containment of waste water will likely be located ……in the north shoulder of the road right of way on
the CSLT property or in the land north east of the site on the bank of the detention basin (shown in
purple shading above, about 20’ x 130’) which straddles the property line.
The site needs could vary during the various phases of drilling, well development, and aquifer testing
and we can work with you to minimize site access impacts to Liberty Utilities.
Equipment
Drilling: A LS 250 MiniSonic™ Rig will be used for the drilling program. The MiniSonic™ Rig is a compact ,
low ground pressure drilling rig designed for drilling in environmentally sensitive areas. Technical
APN 023-30-109
APN 023-30-111
Maximum Work Site Area (proposed)
Formatted: Not Highlight
Formatted: Not Highlight
Formatted: Not Highlight
Comment [IB1]: Sachi- Please complete.
Comment [SI2]: Note – am enquiring re
weekend work which could further limit duration on site and site access.
South Y Feasibility
Pre-Design Investigation
Site Access Agreement Information
information for the drilling equipment is attached. In addition to the drill rig and guide rig, an area for
equipment and casing as well as storage bins for waste will be needed.
Well Development and Aquifer Testing: After the drilling is complete, the drill rig and equipment will be
removed, and replaced with pump and tanks for temporary containment of waste water and a small
water treatment unit.
Schedule
The drilling and testing program is anticipated to be completed within 30 days, including Contractor
mob./demob., on and off the work site. The project is intended to be completed on or before June 1st,
2018.