fr_3004_5-25-22DATE JOB NO.3DJHRI
PROJECT
LOCATION
OWNER
CONTRACTOR
WEATHER TEMP
° F at
°F at
PRESENT AT SITE
6LHUUD0DQRU'ULYH6XLWH
Reno, Nevada 89511
phone (775) 851-8205
fax (775) 851-8593
FIELD REPORT
THE FOLLOWING WAS NOTED
Report No.
IN HOUSE ROUTE TO: EMAIL:
JAD___
Submitted by
CONCRETE FIELD TEST SUMMARY
0L[1R 6SHF6WUHQJWK36, &RQFUHWH *URXW 0RUWDU 2WKHU
7UXFN1R /RFDWLRQ &\OV7DNHQ 6OXPS³ $LU&RQWHQW &RQF7HPS)
05/25/22 3004
STPUD 2022 BOWERS & BIJOU 2/3 WATERLINES -
TASK ORDER NO. 20
South Lake Tahoe, CA
South Tahoe Public Utility District
Vinciguerra Construction
Adrian Combes
SOUTH TAHOE PUBLIC UTILITY DISTRICT
1275 Meadow Crest Drive
South Lake Tahoe, CA 96150 Clear/Calm
Vinciguerra crew (8)
acombes@stpud.us
jryan@stpud.us
5
55
76
CME personnel arrived on-site of the Bijou waterline replacement project in South Lake Tahoe. Arrived on
Fairway at 8:00am and as crew prepared to head south on Fairway.
The Vinciguerra crew (1 operator, Jim and 9 Underground Utility Pipe Fitters, 1 Truck Driver) arrived and
continued up Fairway to the Blackwood “T”. The pipe had to be lowered in the intersection to achieve proper
clearance with the existing sewer. Two, 45 degree fittings were used to lower the pipe and two more were used to
bring back to normal depth. An 8’’ T w/3 8’’ gate valves was placed at station 17+80 Lt Fairway with hydrant valve
placed at 17+95 Lt Fairway. Kickers of concrete was placed at the 45s and behind the valves at the vertical offset.
The crew placed 6” of aggregate base to be used as bedding under the C900 DR 18 or DR14, pipe placed on
top of it. The DR 14 is used in conjunction with bell restraints where we go under the sewer or where we are within
10’ of sewer mainline. They then placed base up to spring line and water jetted it to make sure there were no voids
under the pipe. 1’ of aggregate base was then placed over the pipe and compacted by jumping jack whackers.
95% of the maximum dry density is required on base and testing was performed. The maximum dry density of the
base is a 132.6 at 7.2% moisture as provided by CME on 5-18-22. The results of the testing can be found in this
report. The native material that was placed was also tested using a 119.6 maximum dry density and 11.5%
moisture. These numbers were also provided by the CME laboratory. Results for this testing can also be found in
this report as well as 1 from Thursday that was back calculated. Although the the specifications call for 95% had
been informed by Adrian with STPUD that 90% would be satisfactory on the intermediate backfill. A compaction
wheel attached to an excavator was used for compaction efforts.
The mole was used once again to install long side services at 1098, 1078 Fairway.
Lay out was also performed at the south end of Fairway along with Vanda Lee and Osgood on the Bowers
project. Austerman was on-site to perform saw cutting in these areas along with service areas in various locations.
Departed site 1730 as crew continued clean up.
JVL____
08:00 AM
PM18:00
DocuSign Envelope ID: 64A21110-5E9F-4C8C-B2BB-73B2D4E202CA
'$7( -2%12
352-(&7
/2&$7,21
2:1(5
&2175$&725
:($7+(5 7(03
) DW $0
) DW30
35(6(17$76,7(
6LHUUD0DQRU'ULYH6XLWH
5HQR 1HYDGD
SKRQH
ID[
FIELD REPORT
7+()2//2:,1*:$6127('
5HSRUW1R
,1+286(5287(72 (0$,/
-$'BBB
Submitted by
FIELD DENSITY SUMMARY
7HVW
1R
0DWHULDO'HVFULSWLRQ(OHYDWLRQ
,Q3ODFH
'U\
'HQVLW\
3&)
,Q3ODFH
0RLVWXUH
&RQWHQW
2SWLPXP
0RLVWXUH
&RQWHQW
0D[LPXP
'U\
'HQVLW\
3&)
,Q3ODFH
&RPSDFWLRQ
6SHFLILHG
5HODWLYH
&RPSDFWLRQ
0LQ0DWHULDO 6RXUFH
)* )LQLVK*UDGH6* 6XEJUDGH5* 5RXJK*UDGH2* 2ULJLQDO*UDGH)7* )RRWLQJ*UDGH%& %DVH&RXUVH3UHIL[% %HORZ
3DJHRI
*DXJH,QIR
6RLOV'HQVLW\5HVXOWV
0RGHO6HULDO1R'DWHRI&DOLEUDWLRQ6WG&RXQW
0HWKRGRI0HDVXUHPHQW
0DNH
5HODWLYH7HVW
'HSWK
LQ
6WG&RXQW
05/25/22 3004
STPUD 2022 BOWERS & BIJOU 2/3 WATERLINES -
TASK ORDER NO. 20
South Lake Tahoe, CA
South Tahoe Public Utility District
Vinciguerra Construction
Adrian Combes
SOUTH TAHOE PUBLIC UTILITY DISTRICT
1275 Meadow Crest Drive
South Lake Tahoe, CA 96150 Clear/Calm
acombes@stpud.us
jryan@stpud.us
5
55
76
08:00
18:00
C 900 DR18 17’
C 900 DR14 20’
Saddles and services were placed at 1098 (long) 1078 (long) 1070 (long) Fairway
8’’ T w\3-8’’ Gate Valves at Station 17+80 Lt Fairway (Intersection with Blackwood)
Hydrant valve places at 17+95 Fairway
Vertical offset per detail 3-D3 Fairway and Blackwood Intersection, 2’ extra depth 20’
The Vinciguerra crew consisted of Jim, operator, Art, Thomas, Chris, Dave, Arron, Chris, and Kieth, Colin,
underground utility pipe fitters. Wayne and Casey Vinciguerra were also on-site.
Equipment on-site- 2 Cat 314C excavators, Cat 304E mini excavator, John Deere 210 skip loader, Cat 299D
skid steer, 4 10 wheelers
JVL____
Aggregate Base, Native
Intersection Fairway and Blackwood
Cinderlite Pit, Trench Spoils
1 3’ BFG
2 1’ BFG
126.5
112.6
8.6 7.2
9.6 11.5
132.6
119.6
95
94
95
90
2
Intersection Fairway and Blackwood
Troxler 3430 37748 08/18/21
Direct
2007
6
10
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
10
6
Density
718Moisture
DocuSign Envelope ID: 64A21110-5E9F-4C8C-B2BB-73B2D4E202CA
3+2726
,QLWLDO
DATE JOB NO.3DJH RI
PROJECT
05/25/22 3004 53
STPUD 2022 BOWERS & BIJOU 2/3 WATERLINES -
TASK ORDER NO. 20
Continuing work at Blackwood and Fairway Intersection Exposing gas at service location 1098 Fairway
Exposing mainline for service work Laying out saw cut south end of Fairway
DocuSign Envelope ID: 64A21110-5E9F-4C8C-B2BB-73B2D4E202CA
3+2726
,QLWLDO
DATE JOB NO.3DJH RI
PROJECT
05/25/22 3004 54
STPUD 2022 BOWERS & BIJOU 2/3 WATERLINES -
TASK ORDER NO. 20
Shoring set at vertical offset Fairway and Blackwood
intersection
Concrete to be used for kickers and thrust blocks at
vertical offset fittings
Working on fittings inside shoring Kickers placed around fittings
DocuSign Envelope ID: 64A21110-5E9F-4C8C-B2BB-73B2D4E202CA
3+2726
,QLWLDO
DATE JOB NO.3DJH RI
PROJECT
05/25/22 3004 55
STPUD 2022 BOWERS & BIJOU 2/3 WATERLINES -
TASK ORDER NO. 20
Saw cut south end of Fairway Compaction efforts in service area
Compaction efforts intersection Fairway and Blackwood
DocuSign Envelope ID: 64A21110-5E9F-4C8C-B2BB-73B2D4E202CA