Quick Log_KLHV3 - 053120231
STPUD QUICK LOG
Day & Date Wednesday 5-31-2023 Transcribe: ____Yes
__x__No
Project: Keller Heavenly Improvements Phase 3 (KLHV3) – 2022 Work
Contractor: White Rock Construction Company Inspector: Buck McLelland
Today’s Weather Forecast: Chance of Precipitation:__20___%
Partly cloudy with a slight chance of Thunderstorms in PM Winds light except by thunderstorms
Crews and Equipment on site:
_1_ Project Manager _3_ Operator _1_Truck Driver
_1_ Foreman _4_ Laborer
EQUIPMENT
__ Excavator 328 _1_ Loader 928 __ End Dump Truck _3_ Work Truck
_2_ 10 Wheel Dump Truck __ Skip Loader __ Water Truck __ Air compressor
_1_ Excavator CAT 309 __ TC Truck _1_CAT 316 Excavator
Contractor Requests (shutdowns, pours, etc.):
Tests:
Service/Utility Hits:
Potential Change Order Items/T&M:
Manhole ended up being an existing old PRV discussing removal of unit
Work Completed Today:
Dug trenches for hot tap Working on installing pipe up road to tank Investigate location and layout
of hydrants for the portable Booster pump
Notes: (Visitors, Incidents, Accidents):