Quick Log_KLHV3 - 060220231
STPUD QUICK LOG
Day & Date: Friday 6-2-2023 Transcribe: ____Yes __x__No
Project: Keller Heavenly Improvements Phase 3 (KLHV3) – 2022 Work
Contractor: White Rock Construction Company Inspector: Buck McLelland
Today’s Weather Forecast: Chance of Precipitation:_10____%
Partly Cloudy with a slight chance of Afternoon thunderstorms High temp 74
Crews and Equipment on site:
_1_ Project Manager _3_ Operator _1_Truck Driver
_1_ Foreman _4_ Laborer
EQUIPMENT
__ Excavator 328 _1_ Loader 928 __ End Dump Truck _3_ Work Truck
_2_ 10 Wheel Dump Truck __ Skip Loader __ Water Truck
_1_ Mini Excavator CAT 304 __ TC Truck _1_CAT 304.5 Mini Excavator
Contractor Requests (shutdowns, pours, etc.):
Tests:
Service/Utility Hits:
Potential Change Order Items/T&M:
Work Completed Today:
Hot Tap of both pipes were completed by contractor with no issues. Dug trench for suction line with
Monitor Hydrant and installed piping. Backfilled and cold mix Continue work up road to tank
installing both pipes. Contractor used locating tool to investigate layout of existing piping at the
Wildwood Saddle intersection up to Sitzmark condominium Complex
Notes: (Visitors, Incidents, Accidents):