Loading...
Quick Log_KLHV3 - 060320231    STPUD QUICK LOG Day & Date: Monday 6-5-2023 Transcribe: ____Yes __x__No Project: Keller Heavenly Improvements Phase 3 (KLHV3) – 2022 Work Contractor: White Rock Construction Company Inspector: Buck McLelland Today’s Weather Forecast: Chance of Precipitation:__40___% Chance of Afternoon thunderstorms Strong outfall winds and potential heavy precipitation High of 71 Crews and Equipment on site: _1_ Project Manager _3_ Operator _1_Truck Driver _1_ Foreman _4_ Laborer EQUIPMENT __ Excavator 328 _1_ Loader 928 __ End Dump Truck _3_ Work Truck _2_ 10 Wheel Dump Truck __ Skip Loader __ Water Truck _1_ Mini Excavator CAT 304 __ TC Truck _1_CAT 304.5 Mini Excavator Contractor Requests (shutdowns, pours, etc.): Tests: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Saw cut dig and install 4 inch piping on discharge side of portable booster station Backfill and install cold mix Continue work installing pipe up road to tanks Continue investigation into layout of Wildwood Keller intersection Notes: (Visitors, Incidents, Accidents):