STPUD QUICK LOG
Day & Date: Monday 6-5-2023 Transcribe: ____Yes __x__No
Project: Keller Heavenly Improvements Phase 3 (KLHV3) – 2022 Work
Contractor: White Rock Construction Company Inspector: Buck McLelland
Today’s Weather Forecast: Chance of Precipitation:__40___%
Chance of Afternoon thunderstorms Strong outfall winds and potential heavy precipitation High of 71
Crews and Equipment on site:
_1_ Project Manager _3_ Operator _1_Truck Driver
_1_ Foreman _4_ Laborer
EQUIPMENT
__ Excavator 328 _1_ Loader 928 __ End Dump Truck _3_ Work Truck
_2_ 10 Wheel Dump Truck __ Skip Loader __ Water Truck
_1_ Mini Excavator CAT 304 __ TC Truck _1_CAT 304.5 Mini Excavator
Contractor Requests (shutdowns, pours, etc.):
Tests:
Service/Utility Hits:
Potential Change Order Items/T&M:
Work Completed Today:
Saw cut dig and install 4 inch piping on discharge side of portable booster station Backfill and install
cold mix Continue work installing pipe up road to tanks Continue investigation into layout of
Wildwood Keller intersection
Notes: (Visitors, Incidents, Accidents):