Quick Log_KLHV3 - 060620231    STPUD QUICK LOG Day & Date: Tuesday 6-6-2023 Transcribe: ____Yes __x__No Project: Keller Heavenly Improvements Phase 3 (KLHV3) – 2022 Work Contractor: White Rock Construction Company Inspector: Buck McLelland Today’s Weather Forecast: Chance of Precipitation:_____% Crews and Equipment on site: _1_ Project Manager _3_ Operator _1_Truck Driver _1_ Foreman _4_ Laborer EQUIPMENT __ Excavator 328 _1_ Loader 928 __ End Dump Truck _3_ Work Truck __ 10 Wheel Dump Truck __ Skip Loader __ Water Truck _1_ Mini Excavator CAT 304 __ TC Truck _1_CAT 304.5 Mini Excavator Contractor Requests (shutdowns, pours, etc.): Tests: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Continue working to lay pipe up road to tank Keller and Saddle intersection finish backfill and final grade of hydrants Clean up work area at intersection Mobilize crew to intersection of Wildwood and Keller. Pothole to find high pressure line and get true alignment of line. Redesign entire placement of PRV vault. Notes: (Visitors, Incidents, Accidents):