Quick Log_KLHV3 - 060620231
STPUD QUICK LOG
Day & Date: Tuesday 6-6-2023 Transcribe: ____Yes __x__No
Project: Keller Heavenly Improvements Phase 3 (KLHV3) – 2022 Work
Contractor: White Rock Construction Company Inspector: Buck McLelland
Today’s Weather Forecast: Chance of Precipitation:_____%
Crews and Equipment on site:
_1_ Project Manager _3_ Operator _1_Truck Driver
_1_ Foreman _4_ Laborer
EQUIPMENT
__ Excavator 328 _1_ Loader 928 __ End Dump Truck _3_ Work Truck
__ 10 Wheel Dump Truck __ Skip Loader __ Water Truck
_1_ Mini Excavator CAT 304 __ TC Truck _1_CAT 304.5 Mini Excavator
Contractor Requests (shutdowns, pours, etc.):
Tests:
Service/Utility Hits:
Potential Change Order Items/T&M:
Work Completed Today:
Continue working to lay pipe up road to tank Keller and Saddle intersection finish backfill and final
grade of hydrants Clean up work area at intersection Mobilize crew to intersection of Wildwood and
Keller. Pothole to find high pressure line and get true alignment of line. Redesign entire placement of
PRV vault.
Notes: (Visitors, Incidents, Accidents):