Quick Log_KLHV3 053020231
STPUD QUICK LOG
Day & Date: Tuesday 5/30/23 Transcribe: ____Yes __x__No
Project: Keller Heavenly Improvements Phase 3 (KLHV3) – 2022 Work
Contractor: White Rock Construction Company Inspector: Buck McLelland
Today’s Weather Forecast: Chance of Precipitation:_10 %
Partly Cloudy With a slight chance of thunderstorams after 2 pm
Crews and Equipment on site:
1 Project Manager 3 Operator 1 Truck Driver
2 Foreman 4 Laborer
EQUIPMENT
__ Excavator 328 _1_ Loader 928 __ End Dump Truck _3_ Work Truck
_2_ 10 Wheel Dump Truck __ Skip Loader __ Water Truck __ Air compressor
_1_ Excavator CAT 309 __ TC Truck _1_CAT 316 Excavator
Contractor Requests (shutdowns, pours, etc.):
Tests:
Service/Utility Hits:
Potential Change Order Items/T&M:
Found Manhole that is possibly FI for sewer system
Work Completed Today:
Saw cutting for trench on suction side of Portable booster station
Excavate to find existing pipes for hot taps saddles
Notes: (Visitors, Incidents, Accidents):