Quick Log_KLHV3 053020231    STPUD QUICK LOG Day & Date: Tuesday 5/30/23 Transcribe: ____Yes __x__No Project: Keller Heavenly Improvements Phase 3 (KLHV3) – 2022 Work Contractor: White Rock Construction Company Inspector: Buck McLelland Today’s Weather Forecast: Chance of Precipitation:_10 % Partly Cloudy With a slight chance of thunderstorams after 2 pm Crews and Equipment on site: 1 Project Manager 3 Operator 1 Truck Driver 2 Foreman 4 Laborer EQUIPMENT __ Excavator 328 _1_ Loader 928 __ End Dump Truck _3_ Work Truck _2_ 10 Wheel Dump Truck __ Skip Loader __ Water Truck __ Air compressor _1_ Excavator CAT 309 __ TC Truck _1_CAT 316 Excavator Contractor Requests (shutdowns, pours, etc.): Tests: Service/Utility Hits: Potential Change Order Items/T&M: Found Manhole that is possibly FI for sewer system Work Completed Today: Saw cutting for trench on suction side of Portable booster station Excavate to find existing pipes for hot taps saddles Notes: (Visitors, Incidents, Accidents):