Quick Log TKSPSR_060723STPUD QUICK LOG Day & Date: Wednesday 06/07/23 Transcribe: Yes No Project: Tahoe Keys Pump Station Replacement Contractor: T&S Construction Inspector: M. Mendoza Today’s Weather Forecast: Chance of Precipitation:40%, showers and t-storms after 2pm Mostly sunny, high 68°, north wind 5mph Crews and Equipment on site: 1 Foreman: Joe __ Operator 2 Laborers: Zippy, Miguel __ Truck Driver __ Welder __ Electrician EQUIPMENT 1 Work Truck – 1 Ton Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Site cleanup (remove pallets), install 2 – 2” sump pumps to dewater the excavation between new wet well and valve vault Notes: (Visitors, Incidents, Accidents):