Loading...
Quick Log TKSPSR_062023STPUD QUICK LOG Day & Date: Tuesday 06202023 Transcribe: Yes No Project: Tahoe Keys Pump Station Replacement Contractor: T&S Construction Inspector: M. Mendoza Today’s Weather Forecast: Chance of Precipitation: 0% Sunny, Highs near 59°, West winds 5-10mph. Crews and Equipment on site: Crew: 1 Foreman: Joe Operator: 2 Laborers: Devon, John Truck Driver: Welder : Electrician: Equipment: 1 Work Truck – 1 Ton 1 VOLVO mini ex ECR40D 1 Crane Broderson IC-80 Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Continue assembling 10” ductile iron piping Notes: (Visitors, Incidents, Accidents):