Quick Log TKSPSR_062223STPUD QUICK LOG
Day & Date: Thursday 062223 Transcribe: Yes No
Project: Tahoe Keys Pump Station Replacement
Contractor: T&S Construction Inspector: M. Mendoza
Today’s Weather Forecast: Chance of Precipitation: 30%, showers & thunderstorms after 5pm
Partly sunny, Highs near 66°, South winds 5mph
Crews and Equipment on site:
Crew: Offsite by 2pm
1 Foreman: Joe Operator: 2 Laborers: Devon, John
Truck Driver: Welder : Electrician:
Equipment:
1 Work Truck – 1 Ton 1 VOLVO mini ex ECR40D 1 Crane Broderson IC-80
Contractor Requests (shutdowns, pours, etc.):
Tests Performed:
Service/Utility Hits:
Potential Change Order Items/T&M:
Work Completed Today:
Continue assembling 10” ductile iron piping inside the wet well
Notes: (Visitors, Incidents, Accidents):