Loading...
Quick Log TKSPSR_062623STPUD QUICK LOG Day & Date: Monday 062623 Transcribe: Yes No Project: Tahoe Keys Pump Station Replacement Contractor: T&S Construction Inspector: M. Mendoza Today’s Weather Forecast: Chance of Precipitation: 20%, Isolated showers and thunderstorms after 11am Mostly sunny, highs near 68°, west winds 5-10mph Crews and Equipment on site: Crew: Offsite by 3:30pm 1 Foreman: Joe Operator: 2 Laborers: Devon, John (1/2 day) Truck Driver: Welder : Electrician: Equipment: 1 Work Truck – 1 Ton 1 VOLVO mini ex ECR40D 1 Crane Broderson IC-80 Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Cored valve vault for 4” drain line Installed 4” drain line from the vault to just outside of wet well Notes: (Visitors, Incidents, Accidents):