Quick Log TKSPSR_062823STPUD QUICK LOG
Day & Date: Wednesday 062823 Transcribe: Yes No
Project: Tahoe Keys Pump Station Replacement
Contractor: T&S Construction Inspector: M. Mendoza
Today’s Weather Forecast: Chance of Precipitation: 30%, Isolated showers and thunderstorms after 11am
Sunny, highs near 72°, north winds 5mph
Crews and Equipment on site:
Crew: Offsite by 5pm
1 Foreman: Joe Operator: 2 Laborers: Devon, John
Truck Driver: Welder : Electrician:
Equipment:
1 Work Truck – 1 Ton 1 Crane Broderson IC-80 1 Mini Ex
Contractor Requests (shutdowns, pours, etc.):
Tests Performed:
Service/Utility Hits:
Potential Change Order Items/T&M:
Work Completed Today:
Finished installing nonshrink grout at the pipe penetrations at the valve vault and the wet well
Installed 2 sack sand slurry (dry) in and around the piping between the vault and wet well and under the building where the water service left a void
Started excavation for the odor scrubber and the drain line exiting the existing wet well to the new wet well
Notes: (Visitors, Incidents, Accidents):
At about 9:40am the backflow device inside the building on the freshwater line started leaking, I contacted Mike Chieffo to let him know.