Quick Log_UTSPSRSTPUD QUICK LOG
Day & Date: Tue 082223 Transcribe: Yes No
Project: Upper Truckee Pump Station Rehabilitation
Contractor: T&S Construction Inspector: Mendoza
Today’s Weather Forecast: Chance of Precipitation: 30%
Showers and T-Storms after 2pm. Mostly Sunny High 69° S.E. winds 5-10 mph
Crews and Equipment on site:
1 Foreman Joe __ Operator 2 Laborer: John, Devon
__ Truck Driver __ Electrician
Equipment:
1 Work Truck – 1 Ton 1 John Deere Mini Ex
Contractor Requests (shutdowns, pours, etc.):
Tests Performed:
Service/Utility Hits:
Potential Change Order Items/T&M:
Work Completed Today:
Pothole, excavated, exposed and confirmed outside diameter of existing sewer force main exiting pump station. This work is in preparation of having Tap Master perform the line stop.
Started installation of the silt fence and other BMPs
Notes: (Visitors, Incidents, Accidents):