Quick Log_UTSPSR_090523STPUD QUICK LOG
Day & Date: Tue 090523 Transcribe: Yes No
Project: Upper Truckee Pump Station Rehabilitation
Contractor: T&S Construction Inspector: Mendoza
Today’s Weather Forecast: Chance of Precipitation: 0%
Sunny, with a high near 72. Calm wind becoming west around 5 mph in the afternoon.
Crews and Equipment on site:
1 Foreman Joe __ Operator 2 Laborer: John, Devon
__ Truck Driver __ Electrician
Equipment:
1 Work Truck – 1 Ton 1 Volvo ECR40D Mini Ex 1 Bobcat Skidsteer
Contractor Requests (shutdowns, pours, etc.):
Tests Performed:
Service/Utility Hits:
Potential Change Order Items/T&M:
4 hours 1 foreman, 1 labor + mini ex removing fence, cutting shelf for rock enbankment
Work Completed Today:
Installed BMP’s in preparation for the weekend storms
Notes: (Visitors, Incidents, Accidents):
Field meeting Brent Goligoski, Foreman from T&S and myself going over site clean up items on the river side of the structure. Brent wants the falling fence demo’d (no call out in plans),
6” force main bypass demo’d (no call out in plans), change the vertical curb along the back to a new footing for the support beams (no call out in plans).