Quick Log_UTSPSR_090723STPUD QUICK LOG
Day & Date: Thu 090723 Transcribe: Yes No
Project: Upper Truckee Pump Station Rehabilitation
Contractor: T&S Construction Inspector: Mendoza
Today’s Weather Forecast: Chance of Precipitation: 0%
Sunny, with a high near 75. Light and variable wind becoming southwest 5 to 10 mph in the afternoon.
Crews and Equipment on site:
1 Foreman Joe 2 Laborer: John, Devon
Equipment:
1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer
Contractor Requests (shutdowns, pours, etc.):
Tests Performed:
Service/Utility Hits:
Potential Change Order Items/T&M:
8 hour foreman + 1 laborers, 1 work truck + Yanmar SV100 mini excavator placing boulders, filter fabric, BMP’s and back fill with native material, removed more of the old failing fence
Work Completed Today:
T&M work for the day
Notes: (Visitors, Incidents, Accidents):
T&S has scheduled Tap Masters for Tuesday (091923) for the force main bypass