Quick Log_UTSPSR_090723STPUD QUICK LOG Day & Date: Thu 090723 Transcribe: Yes No Project: Upper Truckee Pump Station Rehabilitation Contractor: T&S Construction Inspector: Mendoza Today’s Weather Forecast: Chance of Precipitation: 0% Sunny, with a high near 75. Light and variable wind becoming southwest 5 to 10 mph in the afternoon. Crews and Equipment on site: 1 Foreman Joe 2 Laborer: John, Devon Equipment: 1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: 8 hour foreman + 1 laborers, 1 work truck + Yanmar SV100 mini excavator placing boulders, filter fabric, BMP’s and back fill with native material, removed more of the old failing fence Work Completed Today: T&M work for the day Notes: (Visitors, Incidents, Accidents): T&S has scheduled Tap Masters for Tuesday (091923) for the force main bypass