Quick Log_UTSPSR_091123STPUD QUICK LOG Day & Date: Mon 091123 Transcribe: Yes No Project: Upper Truckee Pump Station Rehabilitation Contractor: T&S Construction Inspector: Mendoza Today’s Weather Forecast: Chance of Precipitation: 0% Sunny, with a high near 75. Light west wind increasing to 5 to 10 mph in the afternoon. Crews and Equipment on site: 1 Foreman Joe 1 Laborer: Devon Equipment: 1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Installed 20 tons of 8”-12” angular to sub-angular rock for the slope east of the driveway Cut the asphalt on the south side of the building in preparation for the concrete curb work Notes: (Visitors, Incidents, Accidents):