Quick Log_UTSPSR_091223STPUD QUICK LOG
Day & Date: Tue 091223 Transcribe: Yes No
Project: Upper Truckee Pump Station Rehabilitation
Contractor: T&S Construction Inspector: Mendoza
Today’s Weather Forecast: Chance of Precipitation: 0%
Sunny, with a high near 76. Calm wind becoming northwest around 5 mph in the afternoon.
Crews and Equipment on site:
1 Foreman Joe 1 Laborer: John
Equipment:
1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer
Contractor Requests (shutdowns, pours, etc.):
Tests Performed:
Service/Utility Hits:
Potential Change Order Items/T&M:
Work Completed Today:
Installed 20 tons of 8”-12” angular rock on the slope east of the driveway.
Started to excavate for the concrete curb on the south side of the driveway
Notes: (Visitors, Incidents, Accidents):