Quick Log_UTSPSR_091223STPUD QUICK LOG Day & Date: Tue 091223 Transcribe: Yes No Project: Upper Truckee Pump Station Rehabilitation Contractor: T&S Construction Inspector: Mendoza Today’s Weather Forecast: Chance of Precipitation: 0% Sunny, with a high near 76. Calm wind becoming northwest around 5 mph in the afternoon. Crews and Equipment on site: 1 Foreman Joe 1 Laborer: John Equipment: 1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Installed 20 tons of 8”-12” angular rock on the slope east of the driveway. Started to excavate for the concrete curb on the south side of the driveway Notes: (Visitors, Incidents, Accidents):