Quick Log_UTSPSR_091423STPUD QUICK LOG Day & Date: Thu 091423 Transcribe: Yes No Project: Upper Truckee Pump Station Rehabilitation Contractor: T&S Construction Inspector: Mendoza Today’s Weather Forecast: Chance of Precipitation: 0% Sunny, with a high near 76. Calm wind becoming east around 5 mph in the afternoon. Crews and Equipment on site: 1 Foreman Joe 1 Laborer: John Equipment: 1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: T&M 6 hours for the extra form work and excavation for the site improvements Work Completed Today: T&S excavated laid out and built the forms for the new concrete work on the south side of the building (including the new curb and slab); they also off hauled an end dump of grubbed out material Notes: (Visitors, Incidents, Accidents):