Quick Log_UTSPSR_091423STPUD QUICK LOG
Day & Date: Thu 091423 Transcribe: Yes No
Project: Upper Truckee Pump Station Rehabilitation
Contractor: T&S Construction Inspector: Mendoza
Today’s Weather Forecast: Chance of Precipitation: 0%
Sunny, with a high near 76. Calm wind becoming east around 5 mph in the afternoon.
Crews and Equipment on site:
1 Foreman Joe 1 Laborer: John
Equipment:
1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer
Contractor Requests (shutdowns, pours, etc.):
Tests Performed:
Service/Utility Hits:
Potential Change Order Items/T&M:
T&M 6 hours for the extra form work and excavation for the site improvements
Work Completed Today:
T&S excavated laid out and built the forms for the new concrete work on the south side of the building (including the new curb and slab); they also off hauled an end dump of grubbed
out material
Notes: (Visitors, Incidents, Accidents):