Quick Log_UTSPSR_091923STPUD QUICK LOG
Day & Date: Tue 091923 Transcribe: Yes No
Project: Upper Truckee Pump Station Rehabilitation
Contractor: T&S Construction Inspector: Mendoza
Today’s Weather Forecast: Chance of Precipitation:10%
Isolated thunderstorms after 5pm. Sunny, with a high near 73. Calm wind becoming northwest around 5 mph in the afternoon. Chance of precipitation is 10%.
Crews and Equipment on site:
T&S: 1 Foreman Joe 2 Laborer: John, Devon
Range Line: 1 Laborer: Josh
Equipment:
T&S: 1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer
Range Line: 1 Work Truck – ½ ton
Contractor Requests (shutdowns, pours, etc.):
Tests Performed:
Air(bubble) test on 18”x10” tapping saddle on force main, gasket continued to leak air, would not seal, laborer with Range Line dimpled the 18” pipe when torquing the saddle bolts (torque
spec is 125ftlbs, torque to 120ftlbs)
Service/Utility Hits:
Potential Change Order Items/T&M:
Work Completed Today:
T&S and Range Line attempted to install the 18”x10” tapping saddle (see test above)
Notes: (Visitors, Incidents, Accidents):