Quick Log_UTSPSR_092023STPUD QUICK LOG Day & Date: Wed 092023 Transcribe: Yes No Project: Upper Truckee Pump Station Rehabilitation Contractor: T&S Construction Inspector: Mendoza Today’s Weather Forecast: Chance of Precipitation:0% Sunny, with a high near 71. Light southwest wind increasing to 10 to 15 mph in the afternoon. Winds could gust as high as 25 mph. Crews and Equipment on site: T&S: 1 Foreman Joe 2 Laborer: John, Devon Equipment: T&S: 1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: T&M 8 hours wood work setting and installing new 4”x8” post on the south side of the building Work Completed Today: T&M + cut keyway for the larger rock at toe of slope on the east side of driveway Notes: (Visitors, Incidents, Accidents):