Quick Log_UTSPSR_092123STPUD QUICK LOG Day & Date: Thu 092123 Transcribe: Yes No Project: Upper Truckee Pump Station Rehabilitation Contractor: T&S Construction Inspector: Mendoza Today’s Weather Forecast: Chance of Precipitation:50% Scattered showers, with thunderstorms also possible after 11am. Snow level 9200 feet. Partly sunny, with a high near 58. Southeast wind 5 to 10 mph becoming southwest in the morning. Crews and Equipment on site: T&S: 1 Foreman Joe 2 Laborer: John, Devon Equipment: T&S: 1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Hand stacked rip rap and cobbles on the south side of the building, completed placing rip rap on the slope east of the driveway. Notes: (Visitors, Incidents, Accidents):