Quick Log_UTSPSR_092123STPUD QUICK LOG
Day & Date: Thu 092123 Transcribe: Yes No
Project: Upper Truckee Pump Station Rehabilitation
Contractor: T&S Construction Inspector: Mendoza
Today’s Weather Forecast: Chance of Precipitation:50%
Scattered showers, with thunderstorms also possible after 11am. Snow level 9200 feet. Partly sunny, with a high near 58. Southeast wind 5 to 10 mph becoming southwest in the morning.
Crews and Equipment on site:
T&S: 1 Foreman Joe 2 Laborer: John, Devon
Equipment:
T&S: 1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer
Contractor Requests (shutdowns, pours, etc.):
Tests Performed:
Service/Utility Hits:
Potential Change Order Items/T&M:
Work Completed Today:
Hand stacked rip rap and cobbles on the south side of the building, completed placing rip rap on the slope east of the driveway.
Notes: (Visitors, Incidents, Accidents):