Quick Log_UTSPSR_103023JCSTPUD QUICK LOG Day & Date: Mon 103023 Transcribe: Yes No Project: Upper Truckee Pump Station Rehabilitation Contractor: T&S Construction Inspector: Conti Today’s Weather Forecast: Chance of Precipitation:0% Sunny, with a high near 56. South wind 5 MPH Crews and Equipment on site: T&S: Foreman Laborer: 2 Laborers Equipment: T&S: 1 Work Truck – 1 Ton 1 Yanmar SV100 mini ex 1 Bobcat Skidsteer Contractor Requests (shutdowns, pours, etc.): Tests Performed: Service/Utility Hits: Potential Change Order Items/T&M: Work Completed Today: Cut and started the Excavation of the new bypass. Bypass was not finished only the 5 ft stub and 90 were installed to the new 10” gate valve. Notes: (Visitors, Incidents, Accidents):