Loading...
070623STPUD QUICK LOG Day & Date: Thursday, July 6th 2023 Project: Secondary Clarifier #2 Rehabilitation Project Contractor: T&S Construction Todav's Weather Forecast: Chance of Precipitation:0—% Transcribe: Yes X No Inspector: G Butz Sunny, with a high near 80. South wind 5 to 10 mph becoming northwest in the afternoon. Crews and Equipment on site: _ Superintendent ,�Z Operatorj� Labored � dJ4 C;�i ./Foreman fir•' ti ./OperatorlLaborer e,�f.r Truck Driver Plumber/Pipefitter _ Electrician i fi r/, - -,/FT EQUIPMENT :Case CX80 Excavator End Dump Truck Bobcat Skidsteer T300 c_-Portable Fuel Cell (1000 Gallon) Portable Light Tower/Power Plant _ Vacuum Truck Work Truck '/z Ton Work truck 1 Ton Ram Super HD _ Water Buffalo vKobelco CK1100G Crane Ditch Witch FX25 Vac Tailer ,� Volvo H091 Loader z--Air Comp C185 49HP (Doosan) Rental Equipment �.Ii„,,,Gr S7/iII.) Contractor Reauests (shutdowns, pours, etc.): ex Tests Performed: 4/,4 Service/Utility Hits: A1114 Potential Change Order Items/T&M: 9/0 Work Comoleted Todav: ll �lu`1Acre�� �dC[i►l�I���R 1/��` �J�1G►�IG f�ky �+� Is�+lr/Fla�- G (�('�� .�jC� 4�rlrw�r �_ �li�+ ac,-P i 4C '`fl blow plpe k AjAe .4 Ve(ll �, X64d feMuJt A6,,' S D,4 rv,, IIJ ftwe e)41, h Notes: Nistors, Incidents, Accidents): CA-K txX &n- Ae .4 ��o, 4yAx,­ hc Ac 1.E#1- Atf.1/1 4/11 p,rssw•r 40A, r 1